The Three-Runway System: A Three-Phase Process
 

Planning: About 2 Years

  • EIA studies
  • Associated design details
  • Funding options
 
Top

Approval: About 1 Year

  • Environmental permit
  • Financial arrangement
  • Other statutory process requirements
Bottom
Top
Implementation: About 8 Years

Implementation: About 8 Years

  • Detailed designs
  • Land formation
  • Construction of related facilities
Bottom

Implementation

* Indicative timeline that is subject to change