Timeline

The building of the third runway is divided into three phases: planning, approval and implementation.

In the planning phase, the Airport Authority will commission statutory Environmental Impact Assessment (EIA) studies and study funding options. A number of approvals from the Government is needed before actual project implementation – land formation and construction of related facilities – can begin. The entire project is estimated to take about 11 years before the three-runway system is commissioned in 2023.

The Three-Runway System: A Three-Phase Process
 

Planning: About 2 Years

  • EIA studies
  • Associated design details
  • Funding options
 
Top

Approval: About 1 Year

  • Environmental permit
  • Financial arrangement
  • Other statutory process requirements
Bottom
Top
Implementation: About 8 Years

Implementation: About 8 Years

  • Detailed designs
  • Land formation
  • Construction of related facilities
Bottom

Implementation

* Indicative timeline that is subject to change